The way to get this is to do the following:
- Set preserve option to the last one No gaps nor leads
- Create the dependency as normal
- Refresh the schedule view (to redraw the effort based on the dependency).
For any existing plans with dependencies you can set the preserve options as per 1 above (No Gaps nor leads) and right click on either the task you wish to have ‘snap’ into place or alternatively perform the right-click level at a higher point to level a larger portion of the plan.